Tuesday 21 April 2015

Flythrough of Elizabeth Quay from MRA Website

A bit of a glimpse of how it will look when completed.
Interesting that much of the construction completion still has a Novermber 2015 timeline. I guess they are going to be pretty busy.

https://youtu.be/2wzvQIUZYsM


Elizabeth Quay April 2015

Elizabeth Quay April 2015
Water area defined and Tunnel entrances to train station looks like it is buried. Not sure if it connects through to anywhere yet.
Ferry Jetty looks like it has the sun covers up, but no sign of the bridge yet.


Saturday 14 March 2015

February 25 2015




And they say this will be finished this year?
Bridge construction at the entrance is underway as well as the Kiosk on the Island.


Wednesday 7 January 2015

Progress January 2015


January 6th 2015.
You can see the definition of the inlet now.
Concrete  poured in for river barriers, and a large concrete pour in the middle, probably for the boardwalk.
You can see the construction of the resurrected chinese restaurant on the "island", and a couple of buildings around the edges.
The ferry Jetty will probably be where the four pylons are sticking out on the left.

Saturday 15 February 2014

17 August 2012


Digging and siteworks begin on the Esplanade.

Wednesday 12 February 2014

Design Concept

So this is what the finished project is heading towards.
My guess is that it will change a little along the way.




Tuesday 11 February 2014

Constructing a drain

26 March 2013
One of the early photos taken.
Esplanade area has been cleared, a couple of drying ponds created, and work begun on the drains(?) near the crane.
The yellow booms in the water are to prevent sediment getting into the river.
William St is closed and Riverside drive has had a slight diversion.